This component called the Contingent Emergency Response Component (CERC) is initially set up by the World Bank as a zero allocation component (funded at US $0.0 million).
Key Details & Function
UPDATE
Ditwah Rehabilitation Projects
The number of projects selected so far for each implementing agency for rehabilitation following damage caused by the DITWAH along with the estimated cost, is shown below.
|
No. |
Implementing Agency |
Districts Covered |
Number of Projects |
Estimated Cost (Rs. Mn) |
|
1 |
Irrigation Department |
2 |
17 |
935 |
|
2 |
Mahaweli Authority of Sri Lanka |
7 |
15 |
1,100 |
|
3 |
Northern Provincial Irrigation Department |
2 |
6 |
925 |
|
4 |
Eastern Provincial Irrigation Department |
3 |
6 |
363 |
|
5 |
Kandy District Secretariat |
1 |
18 |
96 |
|
6 |
Nuwara Eliya District Secretariat |
1 |
13 |
60 |
|
7 |
Badulla District Secretariat |
1 |
20 |
121 |
|
Total
|
— |
95 |
3,600 | |
Out of the 44 projects held by the Irrigation Department, Mahaweli Authority of Sri Lanka, Northern Provincial Irrigation Department, and Eastern Provincial Irrigation Department, work has commenced on 16 projects so far. Out of these, 1 project has been completed. Through the Kandy, Nuwara Eliya, and Badulla District Secretariats, out of the 51 projects, work has commenced on 19 projects so far. Out of those, 2 projects have been completed.
CERC ACTIVITIES