Project Components

Small and Medium Irrigation Infrastructure Rehabilitation Works (SMIIRW)

The Small-scale Micro-Irrigation Infrastructure Rehabilitation Works (SMIIRW) falls under  component 2  of the Integrated Watershed and Water Resources Management Project (IWWRMP) .

The overall goal of Repurposing the US $10 million is to achieve the food security by maintaining nutritional standard, while increasing the crop yield through developing, small and medium scale irrigation infrastructure at a grass-root level. It also aims to directly support the farmer community (through CBOs) on essential rural development.

Objectives

• To provide immediate direct benefits among the vulnerable farmer community, who are affected due to the present economic crisis.

• To ensure the efficiency of water distribution, improvement of water productivity and re-cultivation of abundant fields.

• To provide direct and immediate benefits to the farmers, who are adversely affected by the impact of Covid-19 and affected due to unavailability of chemical fertilizers.

• To uplift livelihoods and ensure the food security of farmer community.

• To contribute for mitigation and adaptation measures on adverse climate changes.

 Implementing Agency
ProvinceDistrictTotal Allocation (Rs. Mn)IDMASLID-NPCID-EPC
SabaragamuwaRathnapura115.9041.7074.20--
Kegalle48.3048.30---
North CentralAnuradhapura150.0041.70108.30--
Polonnaruwa331.6083.30248.30--
CentralKandy41.7041.70---
Nuwara-Eliya83.3083.30---
Matale83.4041.7041.70--
UvaBadulla110.8027.5083.30--
Monaragala293.30208.3085.00--
NorthernVavuniya150.0041.7025.0083.30-
Jaffna176.70--176.70-
Mannar125.0041.70-83.30-
Kilinochchi83.30--83.30-
Mullaitivu41.70--41.70-
EasternBatticaloa141.7041.7016.70-83.30
Trincomalee239.1083.3033.30-122.50
Ampara225.0083.30100.00-41.70
SouthernGalle50.8050.80---
Matara41.7041.70---
Hambantota137.5075.0062.50--
North WesternPuttalam41.7041.70---
Kurunegala79.2062.5016.70--
WesternColombo41.7041.70---
Kalutara83.3083.30---
Gampaha83.3083.30---
Total3000.001389.20895.00468.30247.50

 

Scope of activities are aligned with the IWWRMP-Project Development Objective (PDO)

• Cleaning of water canals in medium and small irrigation systems, and desilting.

• Restoration of dilapidated irrigation structures.

• Restoration of sluice gates, aqua ducts, turnouts with gates and canals (Distribution & Feeder).

• Repairing abandoned small ponds and tanks, such as removal of aquatic invasive weeds in ponds and tanks.

• Repair of flood bunds.

• Recharge the groundwater aquifer by restoration of abundant ponds and tanks.

• Priority shall be given to the sub-projects that severely influence the water conveyance efficacy and mitigate flood hazards.